OAR
166-150-0020
(8) Building
Plans, Publicly-Owned Structures*
Blueprints and
specifications submitted by building contractors or government agencies applying for a
permit to construct government buildings. Used for enforcement of building
codes and reference for later modifications. Includes specifications of type,
grade, and brand of materials used as well as details related to temporary
facilities, job cleanup, deadlines, and other conditions. May also include change
orders or plan modifications submitted after permit approved.
Minimum
retention: (a) If permit issued and structure completed: For the life of the structure
(b) If no
permit issued: 180 days
(c) If
permit issued, but structure not started, completed,
or permit expired: 180 days after expiration date