Rule Caption: Clarify what constitutes “use” of the tax credit rendering the BETC nontransferable.

Adm. Order No.: DOE 12-2012(Temp)

Filed with Sec. of State: 11-16-2012

Certified to be Effective: 11-16-12 thru 5-14-13

Notice Publication Date:

Rules Amended: 330-090-0140, 330-090-0160

Subject: These temporary rules clarify in ORS 469B.167(3) what constitutes “use” of the tax credit rendering the tax credit nontransferable in the Business Energy Tax Credit (BETC) program. The Oregon Department of Energy is adopting a temporary rule that defines “use” as when the tax credit offsets any portion of the project owner’s tax liability.

 Applicants need this term clarified in order to make decisions about the transferability of their tax credit prior to the BETC sunset at the end of this year. The Oregon Department of Energy believes a temporary rule is justified due to the approaching first BETC sunset (December 31, 2012) and that applicants’ recently requested the department to clarify this term. Without this temporary rule, the transferability of tax credits will be uncertain.

Rules Coordinator: Kathy Stuttaford—(503) 373-2127

330-090-0140

Pass-through Option Facilities

(1) A pass-through Partner may purchase a BETC certificate from an applicant with a facility that is otherwise eligible for the tax credit in return for a cash lump-sum pass through payment equivalent to the net present value of the transferable tax credit. For the purposes of these rules, the net present value of the credit for purposes of the pass through payment is calculated based on the formulas below:

(a) For original preliminary certifications issued on or after January 1, 2010:

(A) For a five year tax credit the net present value is determined by taking the total tax credit amount divided by 1.3579. Tax Credit/1.3579

(B) For a one year tax credit the net present value is determined by taking the tax credit amount divided by 1.0309. Tax Credit/1.0309

(b) For original preliminary certifications issued on or before December 31, 2009:

(A) 50 percent BETC more than $20,000 in eligible costs — 33.5 percent pass-through rate.

(B) 50 percent BETC $20,000 or less in eligible costs — 43.5 percent pass-through rate.

(C) 35 percent BETC more than $20,000 in eligible costs — 25.5 percent pass-through rate.

(D) 35 percent BETC $20,000 or less in eligible costs — 30.5 percent pass-through rate.

(E) Homebuilder Installed Renewable Energy Facility or High Performance Home tax credits — 87 percent of tax credit amount.

(c) If an applicant elects to use the pass through option, the net present value of the credit (the pass through payment) for a facility is determined by the date the department issues the initial preliminary certification for the project.

(2) An Investor-Owned Utility may choose to become a utility Pass-through Partner under the provisions of this section or participate as a Pass-through Partner under other Provisions of these rules that would apply to any other Pass-through Partner.

(a) An investor-owned utility (IOU) that complies with this section may choose to become a Utility Pass-through Partner.

(b) Preliminary certification standards and process:

(A) The application for preliminary certification must include an estimate of the total installation cost of the qualifying measures for which the applicant expects to make payments under OAR 330-090-0140(2) for that year.

(B) Within 60 days after an application for preliminary certification of the pass-through is filed, the Director shall decide if it is complete. If it is not complete, the application will be rejected and returned to the applicant. The applicant may resubmit a complete application.

(C) Within 120 days after a completed application is filed, the Director shall notify the applicant of the status of the application, if the applicant has not been notified otherwise the application has been denied.

(D) The application for preliminary certification of the pass-through must include a detailed work plan. The applicant and ODOE must mutually agree upon the work plan and program. The detailed work plan must include:

(i) A copy or reference to any proposed or required OPUC tariff and all evaluations of the program through which the pass-through will be delivered,

(ii) A not to exceed estimate of the total eligible costs that will be incurred for that calendar year with an estimate of the number of rental dwellings that will be affected, and

(iii) An agreement that upon submitting the complete final certification application the applicant will provide a detailed description of each facility owner, site address, facility description or type, number of dwelling units for multifamily facilities, total facility cost, energy savings, energy type saved and tax credit amount passed through.

(c) Final certification standards and process: Final application for a pass-through tax credit must include a summary and total of each facility’s owner, site address, facility description or type, number of dwelling units for multifamily facilities, total facility cost, energy savings, energy type saved and tax credit amount passed through. The applicant must retain records for each facility including all of the information required in 110-090-0130(11) of these rules.

(A) An application must contain:

(i) An itemized list of costs for each rental dwelling unit weatherized, premium efficient appliance, each alternative fuel vehicle, alternative fuel vehicle for company use, and alternative fuel fueling station, and the total facility costs made that period for which the applicant is applying for credit.

(ii) The nominal value of credits for which the applicant applies, not to exceed the total eligible costs multiplied by the existing net present value of the tax credit for the pass-through payment as defined in OAR 330-090-0140(1).

(iii) The name, address, and phone number of the owner of each rental unit, alternative fuel vehicle, or alternative fuel fueling station listed in OAR 330-090-0140(2)(c)(A)(i). A sample selected by the Department of individual weatherization location audit reports will be submitted for at least 15 percent of the facility sites.

(iv) Certification that each rental dwelling unit energy conservation measure (ECM) is a measure that would qualify under or is a measure recommended in an energy audit completed under ORS 469.633(2).

(v) Certification that the ECMs paid for were installed and inspected in accordance with the IOU’s appropriate allowed tariff(s),

(vi) Certification that the ECMs paid for were installed and inspected in accordance with the IOUs’ Model Conservation Standards tariff or equivalent program as approved by ODOE.

(vii) If costs associated with an individual rental dwelling are $50,000 or more or if required by the Director, a written review and summary completed by a certified public accountant, who is not otherwise employed by the facility owner or pass-through partner, of costs paid based on canceled checks, invoices, receipts, a binding contract or agreement, or other documentation as may be required by these rules.

(viii) If a contractor installed fueling station: the name, address, and phone number of the contractor as defined under OAR 330-090-0130(4) of this rule and the site at which the fueling station is installed.

(B) Within 60 days after a complete final certification application is filed, the Director will approve or deny final certification, with reasons for the action. The Director will deny the final certification if the applicant has not complied with the requirements of this rule. No later than 60 days after the Director issues an order denying the final certification, the applicant may request reconsideration as provided in OAR 330-090-0133(5). The Director will approve final certification if:

(i) The applicant provides the owners of existing rental dwelling units listed in OAR 330-090-0140(2)(c)(A)(i) with:

(I) A low-interest loan, as defined by these rules, up to $5,000 per dwelling unit for ECMs included in OAR 330-090-0140(2)(c)(A)(iv);

(II) A cash payment for ECMs included in OAR 330-090-0140(2)(c)(A)(iv). The payment must be a percentage of the cost-effective portion of the energy conservation measures as approved by the Oregon Public Utility Commission, including installation (but not including the dwelling owner’s own labor), not to exceed the cost of those measures; including the net present value of the tax credit for the pass through payment as defined in OAR 330-090-0170(1) for the EMCs at that specific site address the IOU may claim; or

(III) Such other payments approved by the Director to pay for ECMs in rental dwellings. This includes a payment for the net present value of the tax credit that exceeds the amount of the low-interest loan. This payment will apply first to reduce the amount of the loan with the balance paid to the owner of the rental dwelling unit.

(ii) The amount of the credit is the sum of payments and loans listed in OAR 330-090-0140(2)(c)(A)(i) for ECMs that were installed and inspected.

(3) If an applicant uses any portion of the tax credit it may not be transferred, in accordance with ORS 469B.167(3). For the purposes of transferring the tax credit, a tax credit is considered used when any portion of the tax credit offsets any portion of the project owner’s tax liability.

Stat. Auth.: ORS 469.040 & 469.165
Stats. Implemented: ORS 469.185 - 469.225
Hist.: DOE 7-1985, f. 12-31-85, ef. 1-1-86; DOE 3-1989, f. 12-28-89, cert. ef. 1-1-90; DOE 3-1990, f. & cert. ef. 9-20-90; DOE 4-1991, f. & cert. ef. 12-31-91; DOE 2-1993, f. & cert. ef. 1-28-93; DOE 5-1993, f. & cert. ef. 12-14-93; DOE 2-1995, f. 12-12-95, cert. ef. 12-15-95; DOE 3-1996, f. & cert. ef. 11-27-96; DOE 2-1997, f. 12-15-97, cert. ef. 1-1-98; DOE 4-1998, f. 12-14-98, cert. ef. 12-15-98; DOE 2-1999, f. 12-22-99, cert. ef. 1-1-00; DOE 1-2001, f. 10-5-01, cert. ef. 10-8-01; DOE 2-2004, f. & cert. ef. 1-21-04; DOE 3-2004, f. & cert. ef. 7-1-04; DOE 3-2007, f. 11-30-07, cert. ef. 12-1-07; DOE 3-2008, f. & cert. ef. 3-21-08; DOE 2-2009(Temp), f. & cert. ef. 11-3-09 thru 5-1-10; DOE 1-2010, f. & cert. ef. 1-8-10; DOE 4-2010(Temp), f. 5-21-10, cert. ef. 5-27-10 thru 11-2-10; Administrative correction 11-23-10; DOE 14-2010, f. & cert. ef. 11-23-10; DOE 3-2011(Temp), f. 4-15-11, cert. ef. 4-18-11 thru 10-14-11; DOE 6-2011, f. & cert. ef. 9-29-11; DOE 12-2012(Temp), f. & cert. ef. 11-16-12 thru 5-14-13

330-090-0160

Sunset of the Business Energy Tax Credit Program

(1) ORS 315.357 contains the sunset of the Business Energy Tax Credit Program. Applicants must meet the deadlines that apply to their project:

(a) Applicants with a preliminary certification that are unable to demonstrate evidence of beginning construction before April 15, 2011 must receive final certification before January 1, 2013. The Director does not guarantee that a complete final certification application received on or after November 1, 2012 will be processed before January 1, 2013.

(b) Applicants with a preliminary certification that are able to demonstrate evidence of beginning construction before April 15, 2011 must file a complete application for final certification on or before the earlier of the expiration of the preliminary certificate or July 1, 2014.

(2) Applicants with a preliminary certification may apply to the department to demonstrate that construction of the facility began before April 15, 2011.

(a) An application must include at least these items:

(A) A brief update on the progress of the facility.

(B) A construction schedule showing the anticipated completion date.

(C) A statement that the facility will be completed as approved in the preliminary certification.

(D) Evidence of beginning construction, including but not limited to:

(i) A copy of an approved building, grading or other permit issued for the facility, dated prior to April 15, 2011.

(ii) Evidence of site-specific construction activity, for the period on or after the later of preliminary certification or building permit approval and before April 15, 2011.

(iii) Evidence of facility-specific construction activity, for the period on or after preliminary certification and before April 15, 2011.

(b) Evidence of site-specific construction activity may include, but is not limited to:

(A) Paid invoices for completed construction activity.

(B) Timesheets for construction activities linked to the facility site.

(C) Paid rental documentation for construction equipment.

(D) A written report from the project engineer or installer signed under penalties of perjury describing the work that had commenced before April 15, 2011.

(c) Evidence of facility-specific construction activity may include, but is not limited to:

(A) Paid invoices for facility-specific assembly or manufacturing activity.

(B) Timesheets for assembly or manufacturing activities linked to the facility.

(C) A written report from the project engineer or manufacturer signed under penalties of perjury describing the work that had commenced before April 15, 2011.

(d) Applications must be received by the department before October 1, 2012.

(e) The Department will review the provided information and respond to the application within 60 days. As part of its determination, the department may request additional information from the applicant and may perform inspections.

(A) The department will issue a written acceptance letter to applicants who are able to demonstrate evidence of beginning construction. The acceptance letter will state the date by which the applicant must receive final certification to be allowed a credit under ORS 315.354.

(B) The department will issue a letter to applicants who have not provided sufficient evidence of beginning of construction providing reasons for the denial.

(3) Transfer of tax credits issued to an applicant pursuant to OAR 330-90-0133(1)(a)(D). In this section, a transferee means an individual or business that pays the pass-through amount to an applicant that has been issued the tax credit certificate pursuant to 330-0-90-0133(1)(a)(D), and receives a re-issued tax credit certificate in place of the original applicant.

(a) An applicant who has been issued a tax credit certificate pursuant to OAR 330-90-0133(1)(a)(D) may transfer the tax credit to an eligible transferee through the department process provided by these rules, provided the transfer occurs within 12 months of the issuance of the original tax credit certificate.

(b) If an applicant uses any portion of the tax credit it may not be transferred, in accordance with ORS 469B.167(3). For the purposes of transferring the tax credit, a tax credit is considered used when any portion of the tax credit offsets any portion of the project owner’s tax liability.

(c) The department will not provide assistance in locating a transferee.

(d) A tax credit certificate may only be re-issued once, upon a transfer from the applicant to the transferee.

(e) A tax credit certificate may be re-issued in the name of the individual or entity transferee only.

(f) The transferee may not claim the credit for a tax year prior to the year in which the transferee pays for the credit.

(g) The applicant holding the tax credit certificate must submit a complete tax credit transfer application and the required fee to the department. The tax credit transfer application must:

(A) Include an affidavit from the applicant holding the tax credit certificate affirming that no portion of the tax credit has been claimed and that the applicant has received a cash payment equal to the present value of the credit from the transferee, as calculated under these rules.

(B) Provide power of attorney to authorize the department to confirm with the Oregon Department of Revenue that no portion of the tax credit has been claimed.

(C) Include the original tax credit certificate issued to the applicant.

(h) Upon compliance with this rule and any other applicable requirements, the department will re-issue the tax credit certificate to the transferee.

Stat. Auth.: ORS 469.040 & 469.165, 469.185-469.225, OL 2011, Ch. 730(HB 3672
Stats. Implemented: OL 2011, Ch. 730(HB 3672
Hist.: DOE 10-2011, f. & cert. ef. 11-30-11; DOE 8-2012, f. & cert. ef. 7-10-12; DOE 12-2012(Temp), f. & cert. ef. 11-16-12 thru 5-14-13

Notes
1.) This online version of the OREGON BULLETIN is provided for convenience of reference and enhanced access. The official, record copy of this publication is contained in the original Administrative Orders and Rulemaking Notices filed with the Secretary of State, Archives Division. Discrepancies, if any, are satisfied in favor of the original versions. Use the OAR Revision Cumulative Index found in the Oregon Bulletin to access a numerical list of rulemaking actions after November 15, 2012.

2.) Copyright 2013 Oregon Secretary of State: Terms and Conditions of Use

Oregon Secretary of State • 136 State Capitol • Salem, OR 97310-0722
Phone: (503) 986-1523 • Fax: (503) 986-1616 • oregon.sos@state.or.us

© 2013 State of Oregon All Rights Reserved​