Rule Caption: Temporary Rule Revising Dates for development Review Decisions.

Adm. Order No.: CRGC 2-2011(Temp)

Filed with Sec. of State: 6-16-2011

Certified to be Effective: 6-16-11 thru 10-12-11

Notice Publication Date:

Rules Amended: 350-081-0036, 350-081-0042, 350-081-0054

Subject: Currently, the Executive Director of the Gorge Commission must review a development review application for completeness within 14 days after receiving it, and must issue a decision on a standard development review application within 72 days after accepting the application as complete and an expedited review application within 30 days. This temporary rule changes those time periods into goals that the Executive Director will attempt to make.

Rules Coordinator: Nancy A. Andring—(509) 493-3323, ext. 221

350-081-0036

Acceptance of Application

The Executive Director shall review the application for completeness and if complete, shall accept the application for review.

(1) No application shall be accepted until all documented omissions and deficiencies have been corrected by the applicant. The Executive Director shall notify the applicant of all omissions and deficiencies in writing. The Executive Director shall review supplemental application materials to determine if the application is complete.

(2) No application for a proposed use, which is explicitly prohibited by this ordinance, shall be accepted.

(a) The application shall be returned to the applicant.

(b) A letter, signed by the Executive Director, stating that the proposed use is prohibited and citing the guideline which explicitly prohibits the proposed use, shall be sent to the applicant.

(c) Issuance of this letter shall not prohibit the applicant from appealing the decision pursuant to 350-70.

(3) As a goal, the Executive Director shall attempt to accept the application as complete or notify the applicant of omissions and deficiencies within 14 days of receipt of the application. The Executive Director shall attempt to review supplemental materials within 14 days of receipt. The 14-day time periods in this rule are effective retroactively to all development review applications that have been submitted to the Commission and for which the Executive Director has not made a decision.

Stat. Auth.: ORS 196.150, RCW 43.97.015 & 16 U.S.C. sec. 544c(b)

Stats. Implemented: ORS 196.150

Hist.: CRGC 1-2005, f. 5-17-05, cert. ef. 7-1-05; CRGC 2-2011(Temp), f. & cert. ef. 6-16-11 thru 10-12-11

350-081-0042

Decision of the Executive Director

(1) In making a decision on a proposed use or development the Executive Director shall:

(a) Consult with the applicant and such agencies as the Executive Director deems appropriate;

(b) Consider information submitted by the applicant and all other relevant information available;

(c) Consider all comments submitted pursuant to Commission Rule 350-81-040; and

(d) Solicit and consider the comments of the Forest Service.

(2) The Executive Director shall approve a proposed use or development only if it is consistent with the standards of section 6 and the purposes of P.L. 99-663 and Commission Rule 350-81.

(a) In approving a proposed development action, the Executive Director may impose conditions as necessary to ensure consistency with the guidelines of Commission Rule 350-81.

(b) Conditions attached to approval of a proposed development action shall be recorded in county deeds and records to ensure notice of the conditions to successors in interest. The Executive Director’s decision shall include this requirement.

(3) The Executive Director shall issue a decision on a proposed use or development including findings of fact and conclusions of law and any conditions to ensure consistency with the standards of section 6 and the purposes of P.L. 99-663 and Commission Rule 350-81. As a goal, the Executive Director shall attempt to issue a decision within 72 days after acceptance of the application.

(4) The Executive Director shall send a copy of the decision to the applicant, the Forest Service, the applicable state, the four Indian tribal governments, the applicable county and/or city and each person who submitted comments under Commission Rule 350-81-040. The decision shall set forth the rights of appeal under Commission Rule 350-70.

(5) The decision of the Executive Director shall be final unless a Notice of Appeal is filed in accordance with Commission Rule 350-70. An applicant who chooses to proceed with an approved development during the appeal period shall assume all associated risks and liabilities.

(6) The 72-day time period in this rule is effective retroactively to all development review applications that have been submitted to the Commission and for which the Executive Director has not made a decision.

Stat. Auth.: ORS 196.150, RCW 43.97.015 & 16 U.S.C. sec. 544c(b)

Stats. Implemented: ORS 196.150

Hist.: CRGC 1-2005, f. 5-17-05, cert. ef. 7-1-05; CRGC 1-2007, f. 11-1-07, cert. ef. 1-1-08; CRGC 2-2011(Temp), f. & cert. ef. 6-16-11 thru 10-12-11

350-081-0054

Procedures for Expedited Review Process

(1) Applications

(a) Prior to initiating any use or development which requires review and approval by the Executive Director, an application shall be completed pursuant to 350-81-054.

(b) The Executive Director shall accept and review the application pursuant to 350-81-054 for consistency with the appropriate guidelines of this rule.

(c) The Commission may charge a fee for review of applications after a public hearing. The Gorge Commission shall set the fee.

(d) Standard application forms shall be available at the Commission Office, and shall be provided to county and city planning offices for which this ordinance is effective and the Forest Service.

(e) Applications for uses eligible for expedited review shall include the information required for review uses listed in 350-81-032(5). They shall also include elevation drawings if the proposed development would be visible from a key viewing area. The drawing shall show natural grade and finished grade.

(2) Acceptance of Application

(a) The Executive Director shall review the application for completeness, and if complete, shall accept the application for review.

(b) No application shall be accepted until all documented omissions and deficiencies have been corrected by the applicant. The Executive Director shall notify the applicant of all omissions and deficiencies in writing. The Executive Director shall review supplemental application materials to determine if the application is complete.

(c) As a goal, the Executive Director shall attempt to accept the application as complete or notify the applicant of omissions and deficiencies in writing within 14 days of receipt of the application. The Executive Director shall attempt to review supplemental application materials within 14 days of receipt of the materials.

(3) Notice of Development Review

(a) Within 7 days of the acceptance of an application, the Executive Director shall issue notice of a proposed development review. The notice shall provide the following information:

(A) The name of the applicant;

(B) The general and specific location of the subject property;

(C) A brief description of the proposed action;

(D) The deadline for rendering a decision; and

(E) The deadline for filing comments on the proposed action.

(b) The notice shall state that the application and supporting documents are available for inspection at the Commission office during normal working hours.

(c) The notice shall state the applicant must comply with all applicable local, state, and federal laws.

(d) The notice shall be mailed to the Forest Service, the four Indian tribal governments, applicable county or city planning office(s), libraries and other agencies and interested parties that request a notice or that the Executive Director determines should be notified.

(e) A copy of the notice shall be filed in the records of the Commission.

(4) Comment Period: Any interested person or party shall submit written comments within 10 days from the date a notice is sent.

(5) Written Decision

(a) In making a decision on a proposed use or development the Executive Director shall:

(A) Consult with the applicant and such agencies as the Executive Director deems appropriate;

(B) Consider information submitted by the applicant and all other relevant information available;

(C) Consider all comments submitted pursuant to 350-81-054(4); and

(D) Solicit and consider the comments of the Forest Service.

(b) The Executive Director shall approve a proposed use or development only if it is consistent with the standards of section 6 and the purposes of P.L. 99-663 and Commission Rule 350-81.

(A) In approving a proposed development action, the Executive Director may impose conditions as necessary to ensure consistency with the guidelines of Commission Rule 350-81.

(B) Conditions attached to approval of a proposed development action shall be recorded in county deeds and records to ensure notice of the conditions to successors in interest. The Executive Director’s decision shall include this requirement.

(c) The Executive Director shall issue a decision on a proposed use or development including findings of fact and conclusions of law and any conditions to ensure consistency with the standards of section 6 and the purposes of P.L. 99-663 and Commission Rule 350-81. As a goal, the Executive Director shall attempt to issue a decision within 30 days after acceptance of the application.

(d) The decision of the Executive Director shall be final unless a Notice of Appeal is filed in accordance with Commission Rule 350-70. An applicant who chooses to proceed with an approved development during the appeal period shall assume all associated risks and liabilities.

(6) Notice of Decision and Opportunity to Appeal

(a) The Executive Director shall send a copy of a decision issued under the expedited review process to the four Indian tribal governments, the Forest Service, landowners within 200 feet of the perimeter of the subject parcel, and anyone who submitted comments pursuant to 350-81-054(4).

(b) Any person shall be allowed to appeal a decision issued under the expedited review process in accordance with Commission Rule 350-70.

(7) Expiration of Approvals. Approvals issued under the expedited review process shall expire in accordance with the standards for expiration of approvals for review uses (Commission Rule 350-81-044, above).

(8) Changes or Alterations to an Approved Action. Changes or alterations to an approval issued under the expedited review process shall be made in accordance with the standards for changes or alterations to approved actions for review uses (Commission Rule 350-81-046, above).

(9) The time periods in this rule are effective retroactively to all expedited review applications that have been submitted to the Commission and for which the Executive Director has not made a decision.

Stat. Auth.: ORS 196.150, RCW 43.97.015 & 16 U.S.C. sec. 544c(b)

Stats. Implemented: ORS 196.150

Hist.: CRGC 1-2005, f. 5-17-05, cert. ef. 7-1-05; CRGC 2-2011(Temp), f. & cert. ef. 6-16-11 thru 10-12-11

Notes
1.) This online version of the OREGON BULLETIN is provided for convenience of reference and enhanced access. The official, record copy of this publication is contained in the original Administrative Orders and Rulemaking Notices filed with the Secretary of State, Archives Division. Discrepancies, if any, are satisfied in favor of the original versions. Use the OAR Revision Cumulative Index found in the Oregon Bulletin to access a numerical list of rulemaking actions after November 15, 2010.

2.) Copyright 2011 Oregon Secretary of State: Terms and Conditions of Use

Oregon Secretary of State • 136 State Capitol • Salem, OR 97310-0722
Phone: (503) 986-1523 • Fax: (503) 986-1616 • oregon.sos@state.or.us

© 2013 State of Oregon All Rights Reserved​