DEPARTMENT OF ENERGY, ENERGY FACILITY SITING COUNCIL

 

DIVISION 23

NEED STANDARD FOR NONGENERATING FACILITIES 

345-023-0005

Need for a Facility

This division applies to nongenerating facilities as defined in ORS 469.503(2)(e), except nongenerating facilities that are related or supporting facilities. To issue a site certificate for a facility described in sections (1) through (3), the Council must find that the applicant has demonstrated the need for the facility. The Council may adopt need standards for other nongenerating facilities. This division describes the methods the applicant shall use to demonstrate need. In accordance with ORS 469.501(1)(L), the Council has no standard requiring a showing of need or cost-effectiveness for generating facilities. The applicant shall demonstrate need:

(1) For electric transmission lines under the least-cost plan rule, OAR 345-023-0020(1), or the system reliability rule for transmission lines, OAR 345-023-0030, or by demonstrating that the transmission line is proposed to be located within a “National Interest Electric Transmission Corridor” designated by the U.S. Department of Energy under Section 216 of the Federal Power Act;

(2) For natural gas pipelines under the least-cost plan rule, OAR 345-023-0020(1), or the economically reasonable rule for natural gas pipelines, OAR 345-023-0040;

(3) For storage facilities for liquefied natural gas with storage capacity of three million gallons or greater under the least-cost plan rule, OAR 345-023-0020(1), or the economically reasonable rule for liquefied natural gas storage facilities, OAR 345-023-0040.

Stat. Auth.: ORS 469.470 & 469.501
Stats. Implemented: ORS 469.501 & 469.503
Hist.: EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-023-0020

Least-Cost Plan Rule

(1) The Council shall find that the applicant has demonstrated need for the facility if the capacity of the proposed facility or a facility substantially similar to the proposed facility, as defined by OAR 345-001-0010, is identified for acquisition in the short-term plan of action of an energy resource plan or combination of plans adopted, approved or acknowledged by a municipal utility, people's utility district, electrical cooperative, other governmental body that makes or implements energy policy, or electric transmission system operator that has a governance that is independent of owners and users of the system and if the energy resource plan or combination of plans:

(a) Includes a range of forecasts of firm energy and capacity demands and committed firm energy and capacity resources, as defined in OAR 345-001-0010, over the planning period using a reasonable method of forecasting;

(b) Considers and evaluates a reasonable range of practicable demand and supply resource alternatives over the planning period on a consistent and comparable basis. Practicable alternatives are those that are demonstrated to be technically and economically achievable within the time frame considered to meet potential energy or capacity needs;

(c) Uses financial assumptions, including discount rates and treatment of resource lifetimes and end effects that are consistent and comparable between resources;

(d) For electric transmission line facilities, considers alternatives that include but are not limited to:

(A) Implementation of cost-effective conservation, peak load management and voluntary customer interruption as a substitute for the proposed facility;

(B) Construction and operation of electric generating facilities as a substitute for the proposed facility;

(C) Direct use of natural gas, solar or geothermal resources at retail loads as a substitute for use of electricity transmitted by the proposed facility; and

(D) Adding standard sized smaller or larger transmission line capacity;

(e) For natural gas pipeline facilities, considers alternatives that include but are not limited to:

(A) Implementation of cost-effective conservation, peak load management and voluntary customer interruption as a substitute for the proposed facility;

(B) Installation of propane storage systems, facilities to store liquefied natural gas and underground gas storage reservoirs as a substitute for the proposed facility;

(C) Direct use of electricity, solar or geothermal resources at retail loads as a substitute for use of natural gas supplied by the proposed facility; and

(D) Adding standard sized smaller or larger pipeline capacity;

(f) For storage facilities for liquefied natural gas, considers alternatives that include, but are not limited, to:

(A) Implementation of cost-effective conservation, peak load management and voluntary customer interruption as a substitute for the proposed facility;

(B) Installation of propane storage systems, natural gas pipelines and underground gas storage facilities as a substitute for the proposed facility;

(C) Direct use of electricity, solar or geothermal resources at retail loads as a substitute for use of natural gas supplied by the proposed facility; and

(D) Adding smaller or larger liquefied natural gas storage capacity;

(g) Includes the development and evaluation of alternative resource plans to meet forecast energy or capacity needs over the planning time period;

(h) Analyzes the uncertainties associated with alternative resource plans or strategies. The range of uncertainties about the future must be sufficient to test the performance of each alternative resource strategy. The criteria used to evaluate performance of alternative resource strategies must be broad enough to judge the merits of a strategy from a societal perspective;

(i) Aims to minimize long-run total resource costs while taking into account reliability, compatibility with the energy system, strategic flexibility, as defined in OAR 345-001-0010, and external environmental costs and benefits. The value provided by reliability, compatibility with the energy system, strategic flexibility and external environmental costs and benefits may justify actions that increase the total resource cost of the plan. The Council finds that the goals of a least-cost plan are to minimize expected total resource costs for society and the variance in those costs due to uncertainty about future conditions;

(j) Includes a short-term plan of action;

(k) Is consistent with the energy policy of the state as set forth in ORS 469.010. An energy resource plan is consistent with the energy policy of the stateif its short-term plan of action describes actions that must be taken within a two to three year time frame to provide a reasonable assurance that future energy or capacity demands can be met while aiming to minimize total resource cost; and

(L) Was adopted, approved or acknowledged after a full, fair and open public participation and comment process. Such a process is one in which the public has reasonable and timely access to the decision-maker and to information and records legally available to the public.

(2) The Council shall find that a least-cost plan meets the criteria of an energy resource plan described in section (1) if the Public Utility Commission of Oregon has acknowledged the least cost plan.

Stat. Auth.: ORS 469.470 & 469.501
Stats. Implemented: ORS 469.501
Hist.: EFSC 2-1981, f. & ef. 1-19-81; EFSC 5-1981(Temp), f. & ef. 4-27-81; EFSC 7-1981, f. & ef. 6-29-81; EFSC 1-1983(Temp), f. & ef. 5-3-83; EFSC 1-1984, f. & ef. 8-7-84; EFSC 2-1986, f. & ef. 2-21-86; EFSC 7-1986, f. & ef. 9-18-86; EFSC 1-1993, f. & cert. ef. 1-15-93, Renumbered from 345-079-0105 & 345-111-0025; EFSC 5-1993(Temp), f. & cert. ef. 8-16-93; EFSC 1-1994, f. & cert. ef. 1-28-94; EFSC 2-1994, f. & cert. ef. 5-6-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1998, f. & cert. ef 6-2-98; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2007, f. & cert. ef. 5-15-07

345-023-0030

System Reliability Rule for Electric Transmission Lines

The Council shall find that the applicant has demonstrated need for an electric transmission line that is an energy facility under the definition in ORS 469.300 if the Council finds that:

(1) The facility is needed to enable the transmission system of which it is to be a part to meet firm capacity demands for electricity or firm annual electricity salesthat are reasonably expected to occur within five years of the facility's proposed in-service date based on weather conditions that have at least a 5 percent chance of occurrence in any year in the area to be served by the facility;

(2) The facility is consistent with the minimum operating reliability criteria contained in the Western System Coordinating Council Bulk Power Supply Program 1997-2007, dated April 1, 1998, as it applies either internally or externally to a utility system; and

(3) Construction and operation of the facility is an economically reasonable method of meeting the requirements of sections (1) and (2) compared to the alternatives evaluated in the application for a site certificate.

Stat. Auth.: ORS 469.470 & 469.501
Stats. Implemented: ORS 469.501
Hist.: EFSC 9-1980, f. & ef. 12-22-80; EFSC 1-1993, f. & cert. ef. 1-15-93, Renumbered from 345-080-0043; EFCS 5-1993(Temp), f. & cert. ef. 8-16-93; EFCS 1-1994, f. & cert. ef. 1-28-94; EFCS 2-1994, f. & cert. ef. 5-6-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2012, f. & cert. ef. 5-15-12

345-023-0040

Economically Reasonable Rule for Natural Gas Pipelines or Liquified Natural Gas Storage Facilities

The Council shall find the applicant has demonstrated need for a natural gas pipeline that is an energy facility under the definition in ORS 469.300 or a facility that stores liquefied natural gas, if the Council finds that:

(1) The facility is needed to enable the natural gas supply system of which it is to be a part to meet firm capacity demands for natural gas that are reasonably expected to occur within five years following the facility's proposed in-service date based on weather conditions that have at least a 5 percent chance of occurrence in any year in the areato be served by the proposed facility; and

(2) Construction and operation of the facility is an economically reasonable method of meeting the demands described in section (1) compared to the alternatives evaluated in the application for a site certificate.

Stat. Auth.: ORS 469.470 & 469.501
Stats. Implemented: ORS 469.501
Hist.: EFSC 4-1986, f. & ef. 9-5-86; EFSC 1-1993, f. & cert. ef. 1-15-93, Renumbered from 345-125-0040; EFCS 5-1993(Temp), f. & cert. ef. 8-16-93; EFCS 1-1994, f. & cert. ef. 1-28-94; EFCS 2-1994, f. & cert. ef. 5-6-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2012, f. & cert. ef. 5-15-12

The official copy of an Oregon Administrative Rule is contained in the Administrative Order filed at the Archives Division, 800 Summer St. NE, Salem, Oregon 97310. Any discrepancies with the published version are satisfied in favor of the Administrative Order. The Oregon Administrative Rules and the Oregon Bulletin are copyrighted by the Oregon Secretary of State. Terms and Conditions of Use

Oregon Secretary of State • 136 State Capitol • Salem, OR 97310-0722
Phone: (503) 986-1523 • Fax: (503) 986-1616 • oregon.sos@state.or.us

© 2013 State of Oregon All Rights Reserved​