860-029-0001

Purpose

The purpose of this Division is to implement ORS 758.505 through 758.555 and to implement regulations relating to electric utilities and qualifying cogeneration and small power production facilities as provided under Section 210 of the federal Public Utility Regulatory Policies Act of 1978 (PURPA), Public Law 95-617 (16 USC 824a-3).

[Publications: Publications referenced are available from the Agency.]

Stat. Auth.: ORS 183, 756, 757 & 758
Stats. Implemented: ORS 756.040, 757.612 & 758.505 - 758.555
Hist.: PUC 9-1981, f. & ef. 10-29-81 (Order No. 81-755); PUC 21-1984, f. & ef. 9-25-84 (Order No. 84-742); PUC 1-1998, f. & cert. ef. 1-12-98; PUC 2-2001, f. & cert. ef. 1-5-01; PUC 3-2008, f. & cert. ef. 7-8-08

860-029-0005

Applicability of Rules

(1) Except as otherwise provided, these rules shall apply to all interconnection arrangements between a "public utility" as defined by ORS 758.505 and facilities which are qualifying facilities as defined herein. Provisions of these rules shall not supersede contracts existing before the effective date of this rule. At the expiration of such an existing contract between a public utility and a cogenerator or small power producer, any contract extension or new contract shall comply with these rules.

(2) Nothing in these rules limits the authority of a public utility or a qualifying facility to agree to a rate, terms, or conditions relating to any purchase, which differ from the rate or terms or conditions which would otherwise be provided by these rules, provided such rate, terms, or conditions do not burden the public utility's customers.

(3) Within 30 days following the initial contact between a prospective qualifying facility and a public utility, the public utility shall submit informational documents, approved by the Commission, to the qualifying facility which state:

(a) The public utility's internal procedural requirements and information needs;

(b) Any contract offered by the public utility is subject to negotiation;

(c) Avoided costs are subject to change pursuant to OAR 860-029-0080(3); and

(d) That the avoided costs actually paid to a qualifying facility will depend on the quality and quantity of power to be delivered to the public utility. The avoided costs may be recalculated to reflect stream flows, generating unit availability, loads, seasons, or other conditions.

(4) Upon request or its own motion, the Commission may waive any of the Division 029 rules for good cause shown. A request for waiver must be made in writing, unless otherwise allowed by the Commission.

Stat. Auth.: ORS 183, 756, 757 & 758
Stats. Implemented: ORS 756.040 & 758.505 - 758.555
Hist.: PUC 9-1981, f. & ef. 10-29-81 (Order No. 81-755); PUC 7-1982, f. & ef. 7-21-82 (Order No. 82-514); PUC 21-1984, f. & ef. 9-25-84 (Order No. 84-742); PUC 5-1986, f. & ef. 5-15-87 (Order No. 86-488); PUC 14-1987, f. & ef. 11-19-87 (Order No. 87-1154); PUC 8-1995, f. & cert. ef. 8-30-95 (Order No. 95-858); PUC 1-1998, f. & cert. ef. 1-12-98; PUC 6-2011, f. & cert. ef. 9-14-11

860-029-0010

Definitions for Electric Interconnection

(1) "Avoided costs" means the electric utility's incremental costs of electric energy or capacity or both which, but for the purchase from the qualifying facility or qualifying facilities, the electric utility would generate itself or purchase from another source and shall include any costs of interconnection of such resource to the system.

(2) "Back-up power" and "stand-by power" mean electric energy or capacity supplied by a public utility to replace energy ordinarily generated by a qualifying facility's own generation equipment during an unscheduled outage of the facility.

(3) "Capacity" means the average output in kilowatts (kW) committed by a qualifying facility to an electric utility during a specific period.

(4) "Capacity costs" mean the costs associated with supplying capacity; they are an allocated component of the fixed costs associated with providing the capability to deliver energy.

(5) "Cogeneration" means the sequential generation of electric energy and useful heat from the same primary energy source or fuel for industrial, commercial, heating, or cooling purposes.

(6) "Cogeneration facility" means a facility which produces electric energy and steam or other forms of useful energy (such as heat) by cogeneration which are used for industrial, commercial, heating, or cooling purposes. Such a facility must be at least 50 percent owned by a person who is not an electric utility, an electric holding company, an affiliated interest, or any combination thereof.

(7) "Commission" means the Public Utility Commission of Oregon.

(8) "Costs of interconnection" means the reasonable costs of connection, switching, dispatching, metering, transmission, distribution, equipment necessary for system protection, safety provisions, and administrative costs incurred by an electric utility directly related to installing and maintaining the physical facilities necessary to permit purchases from a qualifying facility.

(9) "Demand" means the average rate in kilowatts at which electric energy is delivered during a set period, to be determined by mutual agreement between the electric utility and the customer.

(10) "Electric utility" means a nonregulated utility or a public utility as defined in ORS 758.505.

(11) "Energy" means electric energy, measured in kilowatt hours (kWh).

(12) "Energy costs" means:

(a) For nonfirm energy, the incremental costs associated with the production or purchase of electric energy by the electric utility, which include the cost of fuel and variable operation and maintenance expenses, or the cost of purchased energy;

(b) For firm energy, the combined allocated fixed costs and associated variable costs applicable to a displaced generating unit or to a purchase.

(13) "Firm energy" means a specified quantity of energy committed by a qualifying facility to an electric utility.

(14) "Index rate" means the lowest avoided cost approved by the Commission for a generating utility for the purchase of energy or energy and capacity of similar characteristics including on-line date, duration of obligation, and quality and degree of reliability.

(15) "Interruptible power" means electric energy or capacity supplied by a public utility to a qualifying facility subject to interruption by the electric utility under certain specified conditions.

(16) "Nonfirm energy" means:

(a) Energy to be delivered by a qualifying facility to an electric utility on an "as available" basis; or

(b) Energy delivered by a qualifying facility in excess of its firm energy commitment.

NOTE: The rate for nonfirm energy may contain an element representing the value of aggregate capacity of nonfirm sources.

(17) "Maintenance power" means electric energy or capacity supplied by a public utility during scheduled outages of a qualifying facility.

(18) "Nonregulated utility" means an entity providing retail electric utility service to Oregon customers that is a people's utility district organized under ORS Chapter 261, a municipal utility operating under ORS Chapter 225, or an electric cooperative organized under ORS Chapter 62.

(19) "Primary energy source" means the fuel or fuels used for the generation of electric energy. The term does not include minimum amounts of fuel required for ignition, start-up, testing, flame stabilization, and control uses; the term does not include minimum amounts of fuel required to alleviate or prevent unanticipated equipment outages and emergencies which directly affect the public health, safety, or welfare.

(20) "Purchase" means the purchase of electric energy or capacity or both from a qualifying facility by an electric utility.

(21) "Public utility" means a utility regulated by the Commission under ORS Chapter 757, that provides electric power to customers.

(22) "Qualifying facility" means a cogeneration facility or a small power production facility as defined by these rules.

(23) "Rate" means any price, charge, or classification made, demanded, observed, or received with respect to the sale or purchase of electric energy or capacity or any rule, regulation, or practice respecting any such price, charge, or classification.

(24) "Sale" means the sale of electric energy or capacity or both by a public utility to a qualifying facility.

(25) "Small power production facility" means a facility which produces electric energy using as a primary energy source biomass, waste, solar energy, wind power, water power, geothermal energy, or any combination thereof. Such facility must be at least 50 percent owned by a person who is not an electric utility, an electric utility holding company, an affiliated interest, or any combination thereof. Only small power production facilities which, with any other facilities located at the same site, have power production capacities of 80 megawatts or less, are covered by these rules.

(26) "Supplementary power" means electric energy or capacity supplied by a public utility, regularly used by a qualifying facility in addition to that which the facility generates itself.

(27) "System emergency" means a condition on a public utility's system which is likely to result in imminent, significant disruption of service to customers, in imminent danger of life or property, or both.

(28) "Time of delivery" means:

(a) In the case of capacity, when the generation is first on line and capable of meeting the capacity commitment of the qualifying facility to the electric utility under the terms of its contract or other legally enforceable obligation.

(b) In the case of firm energy and depending upon the contract between the parties, either:

(A) When the first kilowatt-hour of energy is able to be delivered under the commitment of the qualifying facility; or

(B) When each kilowatt-hour is delivered under the commitment of the qualifying facility.

(29) "Time the obligation to purchase the energy capacity or energy and capacity is incurred" means the earlier of:

(a) The date on which a binding, written obligation is entered into between a qualifying facility and a public utility to deliver energy, capacity, or energy and capacity; or

(b) The date agreed to, in writing, by the qualifying facility and the electric utility as the date the obligation is incurred for the purposes of calculating the applicable rate.

Stat. Auth.: ORS 183, ORS 756, ORS 757 & ORS 758
Stats. Implemented: ORS 756.040 & ORS 758.505 - ORS 758.555
Hist.: PUC 9-1981, f. & ef. 10-29-81 (Order No. 81-755); PUC 7-1982, f. & ef. 7-21-82 (Order No. 82-514); PUC 21-1984, f. & ef. 9-25-84 (Order No. 84-742); PUC 5-1986, f. & ef. 5-15-86 (Order 86-488); PUC 14-1987, f. & ef. 11-19-87 (Order 87-1154); PUC 1-1998, f. & cert. ef. 1-12-98; PUC 9-2001, f. & cert. ef. 3-21-01

860-029-0020

Obligations of Qualifying Facilities to the Electric Utility

The conditions listed in this rule shall apply to all qualifying facilities that sell electricity to a public utility under this Division:

(1) The owner or operator of a qualifying facility purchasing or selling electricity pursuant to these rules shall execute a written agreement with the public utility. The public utility shall file a true copy or summary of the terms of the executed agreement with the Commission within 30 days of the execution of the agreement. If a summary is filed, the summary shall identify the quantity and quality of the power and the price being paid. A true copy of the executed contract shall be available upon request for Commission staff review.

(2) Contracts:

(a) All contracts between a qualifying facility and a public utility for energy, or energy and capacity shall include language which substantially conforms to the following:

This agreement is subject to the jurisdiction of those governmental agencies and courts having control over either party or this agreement. The public utility's compliance with the terms of this contract is conditioned on the qualifying facility submitting to the public utility and to the Public Utility Commission of Oregon, before the date of initial operation, certified copies of all local, state, and federal licenses, permits, and other approvals required by law.

(b) Under subsection (2)(a) of this rule, the public utility shall bear no obligation to identify which approvals are required by law, or to verify the approvals were properly obtained, or that the project is maintained pursuant to the terms of the approvals.

(3) To ensure system safety and reliability of interconnected operations, all interconnected qualifying facilities shall be constructed and operated in accordance with all applicable federal, state, and local laws and regulations.

(4) The qualifying facility shall furnish, install, operate, and maintain in good order and repair, and without cost to the public utility, switching equipment, relays, locks and seals, breakers, automatic synchronizers, and other control and protective apparatus as shown by the public utility to be reasonably necessary to operate the qualifying facility in parallel with the public utility's system, or may contract for the public utility to do so at the expense of the qualifying facility. Delivery shall be at a voltage, phase, power factor, and frequency as specified by the public utility.

(5) Switching equipment capable of isolating the qualifying facility from the public utility's system shall be accessible to the public utility at all times.

(6) At its option, the public utility may choose to operate the switching equipment, described in section (4) of this rule if, in the sole opinion of the public utility, continued operation of the qualifying facility in connection with the public utility's system may create or contribute to a system emergency. Such a decision by the public utility is subject to the Commission's verification pursuant to OAR 860-029-0070. The public utility shall endeavor to minimize any adverse effects on the qualifying facility of the operation of the switching equipment.

(7) Any agreement between a qualifying facility and a public utility shall provide for the degree to which the qualifying facility will assume responsibility for the safe operation of the interconnection facilities.

(8) At its option, the public utility may require a qualifying facility to report periodically the amount of deliveries and scheduled deliveries to the public utility, as shown to be reasonably necessary for the public utility's system operations and reporting.

Stat. Auth.: ORS 183, ORS 756, ORS 757 & ORS 758
Stats. Implemented: ORS 756.040 & ORS 758.505 - ORS 758.555
Hist.: PUC 9-1981, f. & ef. 10-29-81 (Order No. 81-755); PUC 7-1982, f. & ef. 7-21-82 (Order No. 82-514); PUC 21-1984, f. & ef. 9-25-84 (Order No. 84-742); PUC 2-1985, f. & ef. 2-15-85 (Order No. 85-099); PUC 1-1998, f. & cert. ef. 1-12-98

860-029-0030

Obligations of the Public Utility to Qualifying Facilities

(1) Obligations to purchase from qualifying facilities: Each public utility shall purchase, in accordance with OAR 860-029-0040, any energy and capacity in excess of station service (power necessary to produce generation) and amounts attributable to conversion losses, which is made available from a qualifying facility:

(a) Directly from a qualifying facility in its service territory; or

(b) Indirectly from a qualifying facility in accordance with section (4) of this rule.

(2) Obligation to sell to qualifying facilities: Each public utility shall sell to any qualifying facility, in accordance with OAR 860-029-0050, any energy and capacity requested by the qualifying facility on the same basis as available to other customers of the public utility in the same class who do not generate electricity.

(3) Obligation to interconnect: Each public utility shall make such interconnections with any qualifying facility as may be necessary to accomplish purchases or sales under this Division. The obligation to pay for any interconnection costs shall be determined in accordance with OAR 860-029-0060.

(4) Option to wheel power to other electric utilities or to the Bonneville Power Administration: At the request of a qualifying facility, a public utility (which would otherwise be obliged to purchase energy or capacity from such qualifying facility) may transmit (wheel) energy or capacity to any other electric utility or to the Bonneville Power Administration, at the expense of the qualifying facility. Use of a public utility's transmission facilities shall be on a cost-related basis.

(5) Parallel operation: Each public utility shall offer to operate in parallel with a qualifying facility, provided that the qualifying facility complies with the standards established in accordance with OAR 860-029-0020.

(6) When the generating portion of the qualifying facility consumes more electric energy than it produces, the public utility shall cease purchases.

Stat. Auth.: ORS 183, ORS 756, ORS 757 & ORS 758
Stats. Implemented: ORS 756. 040 & ORS 758.505 - ORS 758.555
Hist.: PUC 9-1981, f. & ef. 10-29-81 (Order No. 81-755); PUC 7-1982, f. & ef. 7-21-82 (Order No. 82-514); PUC 21-1984, f. & ef. 9-25-84 (Order No. 84-742); PUC 1-1998, f. & cert. ef. 1-12-98

860-029-0040

Rates for Purchases

(1) Rates for purchases by public utilities shall:

(a) Be just and reasonable to the public utility's customers and in the public interest; and

(b) Be in accordance with this rule, regardless of whether the public utility making such purchases is simultaneously making sales to the qualifying facility.

(2) Establishing rates:

(a) Except for qualifying facilities in existence before November 8, 1978, and except when a public utility fails to make a good faith effort to comply with the request from a qualifying facility to wheel, a purchase rate satisfies the requirements of section (1) of this rule if the rate equals the avoided costs after consideration of the factors set forth in section (5) of this rule.

(b) If a public utility fails to make a good faith effort to comply with the request from a qualifying facility to wheel, the public utility shall purchase at a rate which is the public utility's avoided cost or the index rate, whichever is higher. A good faith effort shall be demonstrated by the public utility's publication of a generally applicable reasonable policy of the public utility to use the public utility's transmission facilities on a cost-related basis.

(c) When the purchase rates are based upon estimates of avoided costs over a specific term of the contract or other legally enforceable obligation, the rates do not violate these rules if any payment under the obligation differs from avoided costs.

(d) Nothing in these rules shall be construed as requiring payment of avoided-cost prices to qualifying facilities in existence before November 1978, provided, however, that prices for such purchases shall be sufficient to encourage continued power production.

(3) Rates for purchases -- time of calculation: Except for the purchases made under section (4) of this rule (standard rates) each qualifying facility shall have the option to:

(a) Provide nonfirm energy as the qualifying facility determines such energy to be available for such purchases, in which case the rates for such purchases shall be based on the purchasing public utility's nonfirm energy avoided cost or if subsection (2)(b) of this rule is applicable, in effect when the energy is delivered; or

(b) Provide firm energy and/or capacity pursuant to a legally enforceable obligation for the delivery of energy and/or capacity over a specified term, in which case the rates for purchases shall be based on:

(A) The avoided costs calculated at the time of delivery, or, if subsection (2)(b) of this rule is applicable, the index rate in effect at the time of delivery; or

(B) At the election of the qualifying facility, exercised at the time the obligation is incurred, the avoided costs, or the index rate then in effect if subsection (2)(b) of this rule is applicable, projected over the life of the obligation and calculated at the time the obligation is incurred.

(4) Standard rates for purchases shall be implemented as follows:

(a) In the same manner as rates are published for electricity sales each public utility shall file with the Commission, within 30 days of Commission acknowledgement of its least-cost plan pursuant to Order No. 89-507, standard rates for purchases from qualifying facilities with a nameplate capacity of one megawatt or less, to become effective 30 days after filing. The publication shall contain all the terms and conditions of the purchase. Except when a public utility fails to make a good faith effort to comply with the request of a qualifying facility to wheel, the public utility's standard rate shall apply to purchases from qualifying facilities with a nameplate capacity of one megawatt or less.

(b) If a public utility fails to make a good faith effort to comply with the request from a qualifying facility to wheel, the public utility shall purchase at a rate which is the public utility's standard rate or the index standard rate, whichever is higher. A good faith effort shall be demonstrated by the public utility's publication of its generally accepted reasonable policy to use the public utility's transmission facilities on a cost-related basis.

(c) The public utility's standard rate may differentiate among qualifying facilities using various technologies on the basis of the supply characteristics of the different technologies.

(5) Factors affecting rates for purchases: In determining avoided costs and for determining the index rate the following factors shall, to the extent practicable, be taken into account:

(a) The data provided pursuant to OAR 860-029-0080(3) and the Commission's evaluation of the data; and

(b) The availability of energy or capacity from a qualifying facility during the system daily and seasonal peak periods, including:

(A) The ability of the public utility to dispatch output of the qualifying facility;

(B) The expected or demonstrated reliability of the qualifying facility;

(C) The terms of any contract or other legally enforceable obligation;

(D) The extent to which scheduled outages of the qualifying facility can be usefully coordinated with scheduled outages of the public utility's facilities;

(E) The usefulness of energy and/or capacity supplied from a qualifying facility during system emergencies, including its ability to separate its load from its generation;

(F) The individual and aggregate value of energy and capacity from qualifying facilities on the public utility's system; and

(G) The smaller capacity increments and the shorter lead times available, if any, with additions of capacity from qualifying facilities.

(c) The relationship of the availability of energy and/or capacity from the qualifying facility as derived in subsection (5)(b) of this rule, to the ability of the public utility to avoid costs, including the deferral of capacity additions and the reduction of fossil fuel use; and

(d) The costs or savings resulting from variations in line losses from those that would have existed in the absence of purchases from a qualifying facility if the purchasing public utility generated an equivalent amount of energy itself or purchased an equivalent amount of energy and/or capacity.

Stat. Auth.: ORS 183, ORS 756, ORS 757 & ORS 758
Stats. Implemented: ORS 756. 040 & ORS 758.505 - ORS 758.555
Hist.: PUC 9-1981, f. & ef. 10-29-81 (Order No. 81-755); PUC 7-1982, f. & ef. 7-21-82 (Order No. 82-514); PUC 21-1984, f. & ef. 9-25-84 (Order No. 84-742); PUC 5-1986, f. & ef. 5-15-86 (Order No. 86-488); PUC 14-1987, f. & ef. 11-19-87 (Order No. 87-1154); PUC 11-1991, f. & cert. ef. 12-5-91 (Order No. 91-1605); PUC 2-1993, f. & cert. ef. 1-8-93 (Order No. 92-1793 & 93-035); PUC 1-1998, f. & cert. ef. 1-12-98

860-029-0050

Rates for Sales

(1) Rates for sales by public utilities shall:

(a) Be just and reasonable and in the public interest; and

(b) Not discriminate against qualifying facilities.

(2) Rates for sales which are based on accurate data and consistent, system-wide costing principles shall be considered not to discriminate against any qualifying facility to the extent that such rates apply to the public utility's other customers with similar load or other cost-related characteristics.

(3) The following additional services shall be provided by a public utility to a qualifying facility at its request:

(a) Supplementary power;

(b) Back-up power;

(c) Maintenance power; and

(d) Interruptible power.

(4) When a waiver request is filed under OAR 860-029-0005(4), the Commission may waive any requirement of section (3) of this rule if, after notice in the area served by the public utility and after opportunity for public comment, the public utility demonstrates and the Commission finds that compliance with such requirement will:

(a) Impair the public utility's ability to render adequate service to its other customers; or

(b) Place an undue burden on the public utility.

(5) The rate for sale of back-up power or maintenance power:

(a) Shall not be based upon an assumption (unless supported by factual data) that forced outages or other reductions in electric output by all qualifying facilities on a public utility's system will occur simultaneously, during the system peak, or both; and

(b) Shall take into account the extent to which scheduled outages of the qualifying facilities can be coordinated usefully with the scheduled outages of the public utility's facilities.

Stat. Auth.: ORS 183, 756, 757 & 758
Stats. Implemented: ORS 756.040 & 758.505 - 758.555
Hist.: PUC 9-1981, f. & ef. 10-29-81 (Order No. 81-755); PUC 7-1982, f. & ef. 7-21-82 (Order No. 82-514); PUC 21-1984, f. & ef. 9-25-84 (Order No. 84-742); PUC 1-1998, f. & cert. ef. 1-12-98; PUC 6-2011, f. & cert. ef. 9-14-11

860-029-0060

Interconnection Costs

(1) Obligation to pay: Any interconnection costs shall be the responsibility of the owner or operator of the qualifying facility. Interconnection costs which may reasonably be incurred by the public utility shall be assessed against a qualifying facility on a nondiscriminatory basis with respect to other customers with similar load or other cost-related characteristics.

(2) Reimbursement of interconnection costs: The public utility shall be reimbursed by the qualifying facility for any reasonable interconnection costs including costs of financing at an interest rate no greater than the effective rate of the public utility's last senior securities issuance at the time of the contract with the qualifying facility. Such reimbursement may be over any agreed period not greater than one-half the length of any contract between the public utility and the qualifying facility when the contract is for a period greater than two years; otherwise, reimbursement shall be made over a one-year period. At the public utility's option and with the Commission's approval, a public utility may guarantee a loan to a qualifying facility for interconnection costs rather than finance such costs from the public utility's own funds.

Stat. Auth.: ORS 183, ORS 756, ORS 757 & ORS 758
Stats. Implemented: ORS 756. 040 & ORS 758.505 - ORS 758.555
Hist.: PUC 9-1981, f. & ef. 10-29-81 (Order No. 81-755); PUC 7-1982, f. & ef. 7-21-82 (Order No. 82-514); PUC 21-1984, f. & ef. 9-25-84 (Order No. 84-742); PUC 1-1998, f. & cert. ef. 1-12-98

860-029-0070

System Emergencies

(1) Qualifying facility's obligation to provide power during system emergencies: A qualifying facility shall be required to provide energy and capacity to a public utility during a system emergency only to the extent:

(a) Provided by agreement between such qualifying facility and public utility; or

(b) Ordered under section 202(c) of the Federal Power Act.

(2) During any system emergency, a public utility may curtail:

(a) Purchases from a qualifying facility if such purchases would contribute to such emergency (including net output requirement); and

(b) Sales to a qualifying facility, as qualified by section (3) of this rule, provided that such curtailment is on a nondiscriminatory basis.

(3) Except in cases of practical impossibility, sales to a qualifying facility which is generating 50 percent or more of its load, shall not be curtailed during a system emergency, or under mandatory curtailments established by Order No. 78-823, until all other customers in its class have been fully curtailed.

(4) A qualifying facility which is unable to deliver power to a public utility owing to curtailment by the public utility shall be relieved of any obligation to sell to the public utility during the curtailment period.

Stat. Auth.: ORS 183, ORS 756, ORS 757 & ORS 758
Stats. Implemented: ORS 756.040 & ORS 758.505 - ORS 758.555
Hist.: PUC 9-1981, f. & ef. 10-29-81 (Order No. 81-755); PUC 7-1982, f. & ef. 7-21-82 (Order No. 82-514); PUC 21-1984, f. & ef. 9-25-84 (Order No. 84-742); PUC 1-1998, f. & cert. ef. 1-12-98

860-029-0080

Electric Utility System Cost Data

(1) Each public utility shall provide sufficient data concerning its avoided costs and costs of interconnection to allow the owner or operator of a qualifying facility to estimate, with reasonable accuracy, the payment it could receive from the utility if the qualifying facility went into operation under any of the purchase agreements provided for in these rules.

(2) By January 1 of each odd-numbered year, each nonregulated utility shall prepare and file with the Commission a schedule of avoided costs equaling the nonregulated utility's forecasted incremental cost of resources over at least the next 20 years.

(3) Each public utility shall file with the Commission draft avoided-cost information with its least-cost plan pursuant to Order No. 89-507 and file final avoided-cost information within 30 days of Commission acknowledgment of the least-cost plan to be effective 30 days after filing. The information submitted shall be maintained for public inspection and include the following data for calculating avoided costs:

(a) The estimated avoided costs on its system, solely with respect to the energy component, for expected levels of purchases from qualifying facilities. The levels of purchases shall be stated in blocks of not more than 100 megawatts for systems with peak demand of 1,000 megawatts or more and in blocks equivalent to not more than 10 percent of the system peak demand for systems of less than 1,000 megawatts. The avoided costs shall be stated on a cents-per-kWh basis, during peak and off-peak periods, by year, for the current calendar year and each of the next five years; and

(b) The public utility's estimated capacity costs at completion of the planned capacity additions and planned capacity firm purchases, on the basis of dollars per kW, and the associated energy costs of each addition or purchase, expressed in cents per kWh. These costs shall be expressed in terms of individual generating resources and of individual, planned firm purchases.

(4) Each public utility contracting to purchase nonfirm energy from a qualifying facility under OAR 860-029-0040(3)(a) shall file with the Commission each quarter its nonfirm energy avoided cost.

(5) Nothing in these rules shall preclude the determination of avoided costs:

(a) As the average avoided costs over an appropriate period of time; or

(b) To reflect variations in avoided costs due to changes in stream flows, generating unit availability, loads, seasons, or other conditions.

(6) State review: Any data submitted by a public utility under this rule shall be subject to review and approval by the Commission. In any such review, the public utility has the burden of supporting and justifying its data. Any standard rates filed under OAR 860-029-0040 shall be subject to suspension and modification by the Commission.

(7) A public utility may propose or the Commission may require a public utility to file the data described in OAR 860-029-0080(3) during the two-year period between filing least-cost plans pursuant to Order No. 89-507 to reflect significant changes in circumstances, such as the acquisition of a major block of resources or the completion of a competitive bid. Such a revision will become effective 90 days after filing.

(8) At least every two years, the public utility must file with the Commission the data described in OAR 860-029-0040(4) and 860-029-0080(3).

Stat. Auth.: ORS 183, ORS 756, ORS 757 & ORS 758
Stats. Implemented: ORS 756.040 & ORS 758.505 - ORS 758.555
Hist.: PUC 9-1981, f. & ef. 10-29-81 (Order No. 81-755); PUC 7-1982, f. & ef. 7-21-82 (Order No. 82-514); PUC 21-1984, f. & ef. 9-25-84 (Order No. 84-742); PUC 2-1993, f. & cert. ef. 1-8-93 (Order No. 92-1793 & 93-035); PUC 1-1998, f. & cert. ef. 1-12-98

860-029-0090

Qualifying Cogeneration and Small Power Production Facilities

18 Code of Federal Regulations (CFR), Part 292, Subpart B, in effect on April 1, 1983, is adopted and prescribed by the Commission as minimum criteria that a cogeneration facility or small power production facility must meet to qualify as a qualifying facility.

[Publications: The publication(s) referred to or incorporated by reference in this rule are available from the agency.]

Stat. Auth.: ORS 183, ORS 756, ORS 757 & ORS 758
Stats. Implemented: ORS 756.040 & ORS 758.505 - ORS 758.555
Hist.: PUC 9-1981, f. & ef. 10-29-81 (Order No. 81-755); PUC 7-1982, f. & ef. 7-21-82 (Order No. 82-514); PUC 21-1984, f. & ef. 9-25-84 (Order No. 84-742); PUC 1-1998, f. & cert. ef. 1-12-98

860-029-0100

Resolution of Disputes for Proposed Negotiated Power Purchase Agreements

(1) This rule applies to a complaint, filed pursuant to ORS 756.500, regarding the negotiation of a Qualifying Facility power purchase agreement. These provisions supplement the generally applicable hearing procedures contained in OAR chapter 860, division 001.

(2) Before a complaint is filed with the Commission, the Qualifying Facility must have followed the procedures set forth in the applicable public utility’s tariff regarding negotiated power purchase agreements.

(3) At any time after sixty calendar days from the date a Qualifying Facility has provided written comments to the public utility regarding the public utility’s draft power purchase agreement, the Qualifying Facility may file a complaint with the Commission asking for adjudication of any unresolved terms and conditions of its proposed agreement with the public utility.

(4) A Qualifying Facility filing a complaint under this rule is the "complainant." The public utility against whom the complaint is filed is the "respondent."

(5) The complaint must contain each of the following, as described by the complainant:

(a) A statement that the Qualifying Facility provided written comments to the utility on the draft power purchase agreement at least 60 calendar days before the filing of the complaint.

(b) A statement of the attempts at negotiation or other methods of informal dispute resolution undertaken by the negotiating parties.

(c) A statement of the specific unresolved terms and conditions.

(d) A description of each party’s position on the unresolved provisions.

(e) A proposed agreement encompassing all matters, including those on which the parties have reached agreement and those that are in dispute.

(6) Along with the complaint, the Qualifying Facility must submit written direct testimony that includes all information upon which the complainant bases its claims.

(7) Within 10 calendar days of service of the complaint, the respondent must file its response with the Commission, addressing in detail each claim raised in the complaint and a description of the respondent's position on the unresolved provisions. The respondent may also identify and present any additional issues for which the respondent seeks resolution.

(8) Along with its response the respondent must submit written direct testimony that includes all information upon which the respondent relies to support its position.

(9) An assigned Administrative Law Judge (ALJ) will conduct a conference with the parties to identify disputed issues, to establish a procedural schedule and to adopt procedures for the complaint proceeding. To accommodate the need for flexibility and to implement the intent of this streamlined complaint process, the ALJ retains the discretion to adopt appropriate procedures provided such procedures are fair, treat the parties equitably, and substantially comply with this rule. Such procedures may include, but are not limited to, hosting a technical workshop, holding a hearing, or submitting written comments.

(10) Only the counterparties to the agreement will have full party status. The ALJ may confer with members of the Commission Staff for technical assistance.

(11) After the hearing, or other procedures set forth in section (9), if the Commission determines that a term or provision of the proposed agreement is not just, fair, and reasonable, it may reject the proposed term or provision and may prescribe a just and reasonable term or provision. The Commission’s review is limited to the open issues identified in the complaint and in the response.

(12) Within 15 business days after the Commission issues its final order, the public utility must prepare a final version of the power purchase agreement complying with the Commission decision and serve it upon the Qualifying Facility. Within 10 days of service of the final power purchase agreement, the Qualifying Facility and the public utility may sign and file the agreement with the Commission, may request clarification whether the agreement terms comply with the Commission order, or may apply for rehearing or reconsideration of the order. The terms and conditions in the power purchase agreement will not be final and binding until the agreement is executed by both parties.

(13) The provisions of any power purchase agreement approved pursuant to this rule apply only to the parties to the agreement and are not to be considered as precedent for any other power purchase agreement negotiation or adjudication.

Stat. Auth.: ORS 183 & 756
Stats. Implemented: ORS 756.040 & 756.500 - 756.575
PUC 3-2008, f. &cert. ef. 7-8-08

The official copy of an Oregon Administrative Rule is contained in the Administrative Order filed at the Archives Division, 800 Summer St. NE, Salem, Oregon 97310. Any discrepancies with the published version are satisfied in favor of the Administrative Order. The Oregon Administrative Rules and the Oregon Bulletin are copyrighted by the Oregon Secretary of State. Terms and Conditions of Use

Oregon Secretary of State • 136 State Capitol • Salem, OR 97310-0722
Phone: (503) 986-1523 • Fax: (503) 986-1616 • oregon.sos@state.or.us

© 2013 State of Oregon All Rights Reserved​